| HEBM Bamboo Fluted Cladding |
||
Raw Material |
4-6 years moso bamboo | |
| Colors | Dark Coffee ![]() |
Teak color ![]() |
| Size | L1850XW137X18/20mm L2000XW137X18/20mm L2440XW137X18/20mm L2900XW137X18/20mm L4200XW137X18/20mm |
|
| Profile |
Flat | 1 Grooved | 2 Grooved ![]() T&G at heads ![]() |
|
| Finish |
Water-based Oil (brand-Woca) Water-based Coating Unfinished |
|
| Moisture Content |
8-12% (Surface value) | |
| Density |
+/-1150g/cm3 | |
| Installation |
Clips Hidden Clips | |
| Life Span |
25 years | |


HEBM & Bamboo Cladding
1. Level the Starter Fastener Row: Begin by installing the bottom row of fasteners. Ensure they are perfectly level using a spirit level.
2. Install the First Board Row: Position the first row of boards level. Engage the groove lip on the board's lower edge securely behind the fastener tabs.
* Verify the fasteners are fully seated within the groove to keep the boards level.
* If needed, carefully tap the boards into place, ideally using a rubber mallet.
* Important: Always secure board ends (end joints) over a structural support (joist/beam) using at least 2 fasteners.
3. Add the Second Fastener Row: Place the next row of fasteners directly onto the top edge of the first installed board row.
4. Install the Second Board Row: Mount the second row of boards onto the newly installed fasteners.
5. Continue Installation: Repeat this process (adding fasteners to the top edge of the previous board row, then installing the next board row) to cover the entire surface.
* Maintain level alignment of all fastener rows throughout.
* Preserve a minimum 5-10 mm ventilation gap at the edges.